NCC / BCA 2019
NCC / BCA 2019 effective as of 1st May 2019 - free download via ABCB website.

https://ncc.abcb.gov.au
Building Activity Management System ('BAMS')
BAMS new VBA Building Permit number and levy system, effective 1st July 2019.

https://vba.vic.gov.au/building/bams
Legislation Reforms
2019 Building Industry Reforms.

"The reforms are designed to achieve compliance and transparency in the building industry, as well as increased consumer protection, so that anyone engaging a building practitioner can do so with confidence."

https://www.vba.vic.gov.au/building/reforms
Codemark Certified Products
A register of all current CodeMark Certificates of Conformity.

https://www.abcb.gov.au/Product-Certification/CodeMark-Certification-Scheme/Certified-Products

Polished Concrete in Wet Areas

There is common misconception of recent, regarding concrete polishing concrete in bathrooms and other wet areas (laundries, toilets, powder rooms, etc). 

Internal wet areas must be waterproofed to stop water transferring through the concrete slab and the wall floor junction.

Bathroom and wet area floors are able to have polished concrete installed, however the correct procedures need to be followed to avoid having the headache of trying to rectify quite a tricky problem at completion of your project. Firstly, consultation will be needed with both your designer/architect and the structural engineer, some previous methods for achieving compliance has been to provide a 100mm set down in the concrete slab, to allow for a 100mm concrete topping slab to be laid (topping slab is the one which gets polished).

Once the concrete slab is poured and cured, a suitable waterproofing membrane applied prior to commencing with the second 100mm concrete topping slab which is poured over the top then allowed to cure. Once cured the concrete polishing can then begin.

This will need to be documented as part of the building permit documentation, as an Alternative Solution would need to be prepared as part of the building permit approval given there is no prescriptive requirements for waterproofing polished concrete floors.

Another potential means of achieving compliance would be via the use of a suitable waterproofing product, however this is subject to the building surveyors assessment of the product specifications and testing to determine whether the desired product can be implemented as part of an Alternative Solution.

Slip resistance should also be considered and necessary precautions taken, always consult your designer or architect for slip resistance guidance when installing hard floor finishes.


17/07/2015

Welcome to the new Building Issues Website

Well, it sure has been a long time in the making, and with a lot of blood sweat and tears along the way, we’re very excited to finally launch our…
READ MORE

16/07/2015

Suitability of Materials for Construction purposes

The Metropolitan Fire Brigade’s Post Incident Analysis Report into the Lacrosse Docklands apartment fire in November 2014 has highlighted the issue of the non-compliant use of building materials, and non-compliant…
READ MORE

16/07/2015

Standards and Tolerances

In response to community expectations the VBA have produced a reference document for an acceptable standard of workmanship to cover potential areas of dispute in domestic construction from preliminary site…
READ MORE

MORE NEWS STORIES